Special Construction Update, Sept. 30, 2010

Final road reconstruction is planned beginning on Monday, October 4th. Northwest Earthmovers Inc. (NEI), and their subcontractors, will begin road reconstruction work on the final segment of Saltzman Road, from just north of Barnes Road to Filbert Street with the goal to have the road within this segment substantially completed by mid-October.

The following is the tentative schedule for the resurfacing work, weather dependent:

Monday, October 4th and Tuesday, October 5th:

  • Milling of existing asphalt surface. (Note that this is not the pulverization of the asphalt as was done previously – the milling will only be deep enough for the installation of a final paving lift)

Wednesday, October 6th (day and night work):

  • Base paving of widened sections adjacent to the Milltown Shopping Center (Walgreens) and Library
  • Final lift paving between Barnes Road and Filbert Street

Thursday, October 7th

  • Installation of temporary striping

Other construction activities for the week include:

  • Continue with the installation of miscellaneous curb, gutter, and sidewalks
  • Continue with the installation of landscaping north of 128th Terrace
  • Installation of railing for Retaining Walls No. 1 and No. 2
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s