Final road reconstruction is planned beginning on Monday, October 4th. Northwest Earthmovers Inc. (NEI), and their subcontractors, will begin road reconstruction work on the final segment of Saltzman Road, from just north of Barnes Road to Filbert Street with the goal to have the road within this segment substantially completed by mid-October.
The following is the tentative schedule for the resurfacing work, weather dependent:
Monday, October 4th and Tuesday, October 5th:
- Milling of existing asphalt surface. (Note that this is not the pulverization of the asphalt as was done previously – the milling will only be deep enough for the installation of a final paving lift)
Wednesday, October 6th (day and night work):
- Base paving of widened sections adjacent to the Milltown Shopping Center (Walgreens) and Library
- Final lift paving between Barnes Road and Filbert Street
Thursday, October 7th
- Installation of temporary striping
Other construction activities for the week include:
- Continue with the installation of miscellaneous curb, gutter, and sidewalks
- Continue with the installation of landscaping north of 128th Terrace
- Installation of railing for Retaining Walls No. 1 and No. 2