Saltzman Road Construction Update, July 15, 2010

Current Activities

  • Continue with construction of Retaining Wall No. 1 (Milltown Shopping Center – Walgreens/Ace Hardware)
  • Grading and installation of new curb, gutter, and sidewalk along east side of Saltzman, between 128th Terrace and the north side of St Pius X
  • Complete installation of new driveways along west side of Saltzman Road between Lovejoy Street and Dogwood Street
  • Complete installation of new chain link fencing along back of walks and walls (all locations)
  • Complete testing of new 8” and 24” water lines and make final connections to existing side streets
  • Complete relocation of all overhead and underground utilities
  • Complete installation of all new underground utilities

Upcoming Activities (2 weeks out)

  • Continue with construction of Retaining Wall No. 1 (Milltown Shopping Center – Walgreens/Ace Hardware)
  • Complete installation of new curb, gutter, and sidewalk along east side of Saltzman, between 128th Terrace and the north side of St Pius X
  • Begin construction and installation of driveways along east side of Saltzman Road, between 128th Terrace and Kearney Street
  • Begin road reconstruction between 128th Terrace and Kearney Street

REMINDER: The project area has been designated a construction zone and the posted speed limit has been temporarily reduce to 25 mph between Cornell Road and the south approach of Bauer Woods Drive (this includes the recently paved portion of the roadway).  All existing traffic restrictions remain in place, including left turn restrictions and school speed zone.

As with most construction activities, there will be noise, dust, and traffic impacts.  The County apologizes in advance for these inconveniences and appreciates your understanding and patience.

Work Hours: 7:00 am – 5:00 pm Monday thru Friday

Lane Restrictions: 9:00 am – 3:30 pm Monday thru Friday

Design Consultant Project Website: http://www.deainc.com/saltzmanroad/

Washington County Project Page:  www.co.washington.or.us/LUT/TransportationProjects/saltzman.cfm

This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s